Kpone landfill: the World Bank-funded dump that filled up, caught fire and was re-engineered

The engineered landfill at Kpone near Tema, funded with World Bank support, opened in 2013. After other Accra dumps closed, it received far more waste than planned, caught fire in August 2019 and was later decommissioned and re-engineered.

Share this article
A waste picker at a landfill site in Ghana
Photo: KwakyeEsther / Wikimedia Commons (CC BY-SA 4.0)

It was designed to take about 500 tonnes of rubbish a day. After the Achimota landfill in Accra closed, waste trucks from across the capital began heading to Kpone, near Tema, and the daily load rose to around 2,000 tonnes. In August 2019, the overloaded site caught fire, and residents later said it was still smouldering months afterwards.

An engineered landfill

The Kpone landfill was built as an engineered facility, meaning it was designed with liners and systems to contain leachate, the toxic liquid produced by decomposing waste. It was funded under a World Bank-supported urban sanitation project and opened in 2013 to serve Tema and its surroundings.

Too much waste

Greater Accra produces thousands of tonnes of solid waste every day. When other disposal sites closed or filled, Kpone became the main destination for much of the region’s rubbish. The site filled far faster than planned.

The fire

In August 2019, a fire broke out at the landfill. Smoke spread over nearby communities in Kpone and Katamanso. Residents complained of breathing problems, and leachate was reported flowing into open drains.

Waste piled up at the Sakumo Ramsar Site near Accra
Waste piled up at the Sakumo Ramsar Site near Accra. Photo: Feliciopedro2 / Wikimedia Commons (CC0)

Re-engineering

The government decided to decommission and re-engineer the site. The contract went to Zoomlion Ghana, and work began on 1 June 2020. The project involved closing and covering the waste, installing a system to collect landfill gas and restoring the land with trees and vegetation. The long-term plan was to turn the site into a recreational area.

Where waste goes now

With Kpone closed for re-engineering, the sanitation ministry secured land at Ayidan in the Ga South Municipality for a new engineered landfill. Accra also relies on transfer stations, recycling and composting facilities, though much waste still ends up in drains, open dumps and the sea.

The plastic problem

Plastic waste, including sachet water bags and food packaging, makes up a large share of Accra’s rubbish. It blocks drains, worsens flooding and pollutes beaches. Recycling businesses have grown, but they handle only part of the volume.

What residents can do

Sort waste where possible, separating plastics and bottles for recyclers. Pay for registered collection services rather than dumping or burning waste. Avoid putting rubbish into drains, which causes flooding in the rainy season.

A recurring crisis

Kpone is one chapter in a long story. Accra has repeatedly opened dumps, filled them and searched for new sites as the city grows.

A landfill is supposed to be where a city’s rubbish disappears. Kpone showed what happens when a city produces more than any single site can hide.

Isaac Nana Yaw Annor

Isaac Nana Yaw Annor, popularly known as King Bygone, is a Ghanaian blogger, publicist and digital publisher, and the editor of Accra Posts. He started out with an entertainment blog, wrote more than 389 articles for Opera News, and worked alongside broadcaster Abeiku Santana on media and publicity from 2016 to 2024. He founded The Gospel Post, We Post Weddings, Nsemwokrom, AfroYard and Culture Gossip, and is a certified software engineer (ALX Africa). Avance Media named him among the Top 50 Ghanaian Bloggers in 2022, 2023 and 2024.

More from Isaac Nana Yaw Annor →