The Obetsebi Lamptey-Pamprom road should reopen by 20 December, GARID says

GARID expects the stretch from Obetsebi Lamptey to Pamprom to reopen between 15 and 20 December after drainage works. Here is what the flood project is building.

Share this article
A busy road in Kaneshie, Accra
Photo: Elodie Ouelo / Wikimedia Commons (CC BY-SA 4.0)

Motorists who have spent the past three months detouring around Kaneshie may get some relief before Christmas. The stretch of road from the Obetsebi Lamptey Interchange to the Metro Mass area at Pamprom Junction is expected to reopen “between December 15 and 20, 2026,” according to the Greater Accra Resilient and Integrated Development (GARID) project, MyJoyOnline reported on 21 November.

“We are targeting around the 15th to 20th of December,” said the project manager, Cephas Ofori. The first phase of the drainage works on the stretch is 90 per cent complete, with backfilling and pavement restoration still to do.

Why the road was closed

The westbound carriageway of the Dr Busia Highway at Pamprom Junction was closed on 7 September 2026 so GARID could build drainage there, MyJoyOnline reported. The project’s coordinator, Dr Ohene Sarfo, advised motorists to avoid Kaneshie if it was not their destination.

The closure was originally meant to end in November. According to the latest update, demolition, excavation, base walls and cover slabs are finished on the first phase, and work on a second phase, from Pamprom Crossing to First Light, has already started.

What GARID is

GARID is a World Bank-funded programme to reduce flooding in Accra’s Odaw River basin. Its original financing was $285 million, MyJoyOnline reported in June, of which $65 million was redirected to Ghana’s Covid-19 response. The World Bank later approved an additional $150 million and extended the project, originally due to end in 2025, to 2027.

Its work includes dredging the Odaw River, widening major drainage channels, removing bridges that restrict the flow of water, and solid waste and community upgrading across the basin. GARID said in June that about $150 million had been committed to contracted works and consultancies across 17 metropolitan, municipal and district assemblies.

The urgency of the work was clear in late June, when heavy rain on 28 and 29 June flooded parts of Accra. MyJoyOnline reported at least three deaths in the Alajo area, and the Ghana News Agency later reported that NADMO had recorded 13 deaths nationally, with about 58,000 people temporarily displaced.

Kaneshie footbridges must wait

The drainage works are also holding up other projects. In August, the Mayor of Accra, Michael Kpakpo Allotey, said the rehabilitation of the Kaneshie Market footbridges could not begin until GARID finished its work in the same corridor, to avoid spending money twice. “Right now, we are just waiting for the GARID workers to finish for us to work on ours,” he told Channel One TV.

Litter in a drainage channel in Accra
Litter in a drainage channel in Accra. Photo: Goldenwabbit / Wikimedia Commons (CC BY-SA 4.0)

What drivers should know

Until the road reopens, the diversions around Kaneshie and Pamprom remain in place. The reopening date is a target, not a guarantee, and it depends on the remaining backfilling and paving being finished on time. Drivers travelling between the Obetsebi Lamptey Interchange and Mallam should allow extra time, especially in the busy weeks before Christmas, and use alternative routes where possible.

For residents of Kaneshie and the communities along the Odaw, the inconvenience comes with a promise: drains built to carry the kind of rain that flooded the city in June.

Isaac Nana Yaw Annor

Isaac Nana Yaw Annor, popularly known as King Bygone, is a Ghanaian blogger, publicist and digital publisher, and the editor of Accra Posts. He started out with an entertainment blog, wrote more than 389 articles for Opera News, and worked alongside broadcaster Abeiku Santana on media and publicity from 2016 to 2024. He founded The Gospel Post, We Post Weddings, Nsemwokrom, AfroYard and Culture Gossip, and is a certified software engineer (ALX Africa). Avance Media named him among the Top 50 Ghanaian Bloggers in 2021, 2022 and 2023. In November 2026 he graduated from the University of Media, Arts and Communication (UniMAC) training programme for bloggers and digital content creators.