VALCO: the Tema aluminium smelter built to use Akosombo’s power

The Volta Aluminium Company smelter at Tema was built in the 1960s as the main customer for electricity from the Akosombo Dam. Once majority owned by American firms, VALCO later came under Ghanaian state ownership and has struggled with power costs and shutdowns.

Share this article
The VALCO Roundabout in Tema
Photo: Hiroo Yamagata / Wikimedia Commons (CC BY-SA 2.0)

When Kwame Nkrumah dreamed of the Akosombo Dam, he needed a customer for its electricity. The answer was an aluminium smelter at Tema, built by American companies and powered by the Volta River. The Volta Aluminium Company, known as VALCO, began production in the late 1960s. For decades it was one of Ghana’s largest industrial plants. Its history, of booms, shutdowns and changes of ownership, mirrors many of the challenges of Ghanaian industry.

The Volta River Project and production

The Akosombo Dam and the VALCO smelter were planned together as part of the Volta River Project, which aimed to industrialise Ghana. VALCO was built and owned mainly by Kaiser Aluminum, with Reynolds Metals holding a smaller share. The smelter began producing aluminium in 1967, using imported alumina rather than Ghana’s own bauxite.

An aluminium smelter
An aluminium smelter. Photo: Jim Barton / Wikimedia Commons (CC BY-SA 2.0)

VALCO received electricity at low prices under its agreement with the Volta River Authority, a deal later criticised as too favourable to the company. Critics noted that Ghana’s bauxite was not used, so the country did not develop a full aluminium industry.

Shutdowns, state ownership and struggles

When droughts lowered water levels at Akosombo, power supply to VALCO was cut, forcing shutdowns. In the 2000s, the Ghanaian government bought out the foreign owners and took control of the smelter. Under state ownership, VALCO has operated below capacity, with power costs and old equipment as major problems. Ghana has announced plans to develop an integrated aluminium industry, linking bauxite mining, refining and smelting.

VALCO has provided jobs for many workers in Tema and supported related businesses. VALCO’s story shows the difficulty of building industries that depend on cheap energy and foreign markets. The smelter remains part of debates about Ghana’s industrial future.

The smelter today and its workers

The smelter’s potlines need steady, affordable electricity to run. When power prices rise or supply becomes unreliable, production is cut, which affects workers and suppliers in Tema. Successive governments have searched for partners to modernise the plant and make it competitive again. Many former VALCO workers live in Tema and have watched the plant’s fortunes rise and fall with each change of government and power price.

VALCO was built to give Akosombo’s electricity a purpose. Half a century later, Ghana is still trying to turn its bauxite, power and smelter into the industry Nkrumah imagined.

Isaac Nana Yaw Annor

Isaac Nana Yaw Annor, popularly known as King Bygone, is a Ghanaian blogger, publicist and digital publisher, and the editor of Accra Posts. He started out with an entertainment blog, wrote more than 389 articles for Opera News, and worked alongside broadcaster Abeiku Santana on media and publicity from 2016 to 2024. He founded The Gospel Post, We Post Weddings, Nsemwokrom, AfroYard and Culture Gossip, and is a certified software engineer (ALX Africa). Avance Media named him among the Top 50 Ghanaian Bloggers in 2022, 2023 and 2024.