Many travellers flying into Accra now arrive through Terminal 3 at Kotoka International Airport, the glass-fronted building that opened to passengers on 15 September 2018. It was built to handle five million passengers a year.
As the Christmas travel season begins and families prepare to meet relatives returning for Detty December, here is how the terminal came to be, what it cost and how it has performed.
From groundbreaking to opening
The project was initiated in October 2015, and ground was broken in March 2016, according to Airport Technology and the Ghana News Agency. Construction was completed in June 2018. MyJoyOnline reported that the terminal “became fully operational on September 15, 2018 following the completion of tests and simulation exercises.”
The design-and-build contractor was the Turkish firm Mapa Construction, with the engineering consultancy Arup responsible for planning, architecture and engineering, and Micheletti as the main civil works subcontractor, according to Airport Technology.
A $250 million building
Ghanaian reports and Airport Technology put the cost of Terminal 3 at $250 million. Airport Technology reported that in 2015 the Ghana Airports Company Limited (GACL) “secured $250m from a consortium of banks led by Ecobank Capital,” and that the African Development Bank approved a $120 million loan, its first private-sector investment in Ghana’s transport sector. The terminal was part of a wider GACL programme valued at about $400 million, which included work at regional airports.
The financing was raised by GACL rather than paid directly from the national budget. In March 2018, before the terminal opened, MyJoyOnline reported that the company had already begun repaying the loans.
What the terminal holds
Terminal 3 has five levels and covers 48,268 square metres, according to Airport Technology and MyJoyOnline. It was designed for five million passengers a year and 1,250 passengers at peak times, with room to expand to 6.5 million.
Passengers pass through 56 check-in desks and, on arrival, a bank of immigration counters and e-gates. The terminal has six boarding bridges, three business lounges and 707 car parking spaces, and its automated baggage system was built to handle about 3,000 bags an hour. Some figures vary between reports. For example, the number of passport control counters is given as 26 in one account and 30 in another.

What it has earned
In February 2023, the then Transport Minister, Kwaku Ofori Asiamah, told Parliament that Terminal 3 had generated more than GH¢136.5 million between September 2018 and December 2022 from private businesses through royalties and rent, GNA reported.
GNA also reported that Kotoka handled about 2.8 million passengers and 46,996 aircraft movements in 2019, the last full year before the Covid-19 pandemic disrupted air travel.
Using Terminal 3 this Christmas
Kotoka sits about 10 kilometres from Accra’s city centre on a site of 1,610 acres, according to Airport Technology. Roads around the airport get busy in December.
If you are collecting someone, check the flight’s arrival time before leaving home and allow extra time for the drive. Arriving passengers should keep their travel documents ready for immigration, and those using the e-gates need to follow the instructions at the gates. For departing travellers, airlines generally ask passengers on international flights to arrive about three hours before departure, and that advice matters more in the busy weeks before Christmas.
