The concourse that will join Terminals 2 and 3 at Accra’s international airport is about a fifth built. “It is already at 20% completion,” Felix Kwakye Ofosu, the government spokesperson, wrote on Facebook on 7 November 2026, MyJoyOnline reported.
The project is meant to ease congestion at an airport that has grown busier in recent years. According to MyJoyOnline, passenger numbers rose from 1.8 million in 2022 to 2.5 million in 2025.
What is being built
The government first announced the project in April. In a post on 3 April, Kwakye Ofosu said: “Work will begin this month on an ultra-modern Concourse connecting Terminals 2 and 3.”
The plans he described include five additional passenger boarding bridges, five passenger holding areas, travelators running in both directions, five new escalators and lifts, a VIP lounge, four business lounges, and four new retail and duty-free pods.
President John Mahama cut the sod for the project in April. A MyJoyOnline photo report on 28 April said the concourse would bring “modern boarding bridges, expanded waiting areas, VIP lounges, retail facilities, and upgraded service infrastructure.”
Who is paying
The government says no state money is going into the concourse. Speaking at the sod-cutting for a separate airport project, a seven-storey car park and hotel complex, on 27 August, Mahama said the Terminal 2 to Terminal 3 concourse was “being funded entirely on the balance sheet of the Ghana Civil Aviation Authority.” He added: “The government of Ghana has not given any of the two institutions one single cedi for these projects.”
Reports have differed on which body is responsible. The April announcement referred to the Ghana Airports Company, while Mahama’s August remarks named the Ghana Civil Aviation Authority as the funder. No cost, contractor or completion date has been given in the reports reviewed for this article.
Why it matters for travellers
Terminal 3 opened in 2018. A direct link to Terminal 2, with five more boarding bridges and five more holding areas, is intended to give the airport more room to handle its growing passenger numbers.
For now, the work is happening alongside normal airport operations. Travellers passing through the airport over Christmas may see construction around the terminals, and should allow extra time, especially in the busy days before and after the holidays.

The 20 per cent figure came seven months after work was announced. The government has not said when it expects the concourse to open. Further progress updates, and details of the cost and contractor, will show whether the project stays on track, and whether the airport will have its extra capacity in time for future peak seasons.